How do I manage a Change Request?

Create, assess and track change requests with impact ratings and tolerances.

Project ManagersProject Manager · Team Member Last updated 16 Oct 2026

Change Requests

A Change Request records a proposed or actual change to the project. It is managed in the Changes area of a project.

Creating a change request

  1. Open a project → Changes.
  2. Select Add Change Request.
  3. Enter a title and description.
  4. Set the change origin — where the change was raised:
    • Meeting
    • Email
    • Conversation
    • Other
  5. Add source details — free text about where the change came from (for example, "Programme Board" or "Supplier Email").
  6. Set the overall impact on a 1–5 scale (1 = Very Low, 5 = Very High).
  7. Complete the tolerances if applicable — time, benefit, cost, scope, risk and quality.
  8. Set the RAG status (green, amber or red) to indicate the delivery concern level.
  9. Save.

Tracking and filtering

  • Filter the Change Log by status, RAG status, impact or origin.
  • The Impact column shows the overall impact rating for each change.
  • Set a review date to track when the change request will be reviewed.

Status

A change request moves through these statuses:

  • Pending — awaiting review.
  • Approved — accepted and in progress.
  • Rejected — declined.
  • Escalated — raised to a higher authority.

Use the RAG status to flag delivery concern. The overall impact rating is for display and prioritisation — it does not feed the Project Health Score.